September 24, 2026: The Los Alamos County Justice Center continues to experience issues from a power outage that began on September 23. The outage is preventing access to in-person court services at this time. Court staff will provide services remotely to the extent possible until Monday, September 28.
The Los Alamos Wastewater Treatment Plant was commissioned in 2004 and has been in operation for 20 years. The equipment at the plant has maintenance issues and is nearing its life expectancy. With several items needing to be addressed, DPU will apply for a $2,000,000 Rural Infrastructure Program (RIP) loan to fund these projects together.
Budget: Aeration Basin Crack Repair $800,000
Motor Controls Centers – Miscellaneous $200,000
Fine Screen $500,000
Blower Building HVAC $200,000
UV Disinfection Replacement $300,000