9th Street

  • Project typeRemoval and Replacement of Deteriorated Sidewalks, Curbs, and Gutter
  • Project value$288,485.07
  • Project scheduleConstruction Phase
  • Contractor nameFranco’s Builders, LLC
  • Completion DateMay 29, 2026

This project includes the removal and replacement of deteriorated sidewalks and  curbs and gutter as well as the installation of new ADA compliant ramps along both the west and east sides of 9th Street from Myrtle to Iris Street . To minimize disruption to residents, the work is being completed in two separate phases.  Work on the west side began on February 23, 2026 and was completed on March 20, 2026. Construction on the east side began on March 26, 2026 and is scheduled for completion on April 20, 2026.

 

 

Location

East and West Sides of 9th Street, Los Alamos, NM 87544  View Map