The fine screen was completed in-house by GWS crews during the summer of 2026. The UV disinfection replacement is scheduled for December 2026.
The Los Alamos Wastewater Treatment Plant was commissioned in 2004 and has been in operation for 20 years. The equipment at the plant has maintenance issues and is nearing its life expectancy. With several items needing to be addressed, DPU will apply for a $2,000,000 Rural Infrastructure Program (RIP) loan to fund these projects together.
Budget: Motor Controls Centers – Miscellaneous $200,000
Fine Screen $500,000 completed 2026
Blower Building HVAC $200,000
UV Disinfection Replacement $300,000 scheduled Dec 2026