Trinity Drive Electrical Replacement Project

  • Project typeElectrical utility upgrade
  • Project scheduleSummer - Winter 2026
  • Contractor nameDub-L-EE
  • Completion DateNovember 13, 2026
map of Trinity from Oppenheimer to Timber Ridge with work zone marked in red box

Update

Phase 1 has been completed. Phase 2 is active on the south side of Trinity Drive, weather permitting. An initial press release was sent out June 12, regarding this project: Sidewalk work to begin on Trinity

Construction operations

  • Flush mounting 3 electrical boxes on the east corner of 17 Street and Trinity Drive will occur on Monday, October 26. Scheduled power outage from 8-12 on that day impacting 1793 Deacon St, 1601 Trinity Dr, and 1650 Trinity Dr. See work zone map below.
  • Crews are scheduled to finish the installation of the conduit and repouring of the sidewalks by the end of October. 
  • North side of Trinity Drive is complete, as of August 21.

Traffic control

  • To ease flow of traffic, please do not turn left onto Timber Ridge Road during high traffic times (there is currently no dedicated turn lane). Drivers are encouraged to only make the right turns onto Timber Ridge Road.  
  • Cones will be present in roadway and lanes will be shifted to allow safe workspace.
  • Follow all work zone signs and exercise caution.

Work zone for scheduled power outage (Mon, Oct 26, 8-12):

map indicating customers impacted by scheduled power outage and work zone

Location

Trinity Drive from Oppenheimer to Timber Ridge, Los Alamos, NM 87544  View Map

Google Map