San Ildefonso Road 8” Waterline Replacement

  • Project typeUtility line replacement
  • Project value$ 2,300,000
  • Project scheduleSummer 2026 - January 2027
  • Completion DateJanuary 29, 2027
Bicycle on road

Update

  • As of Oct. 9, concrete work for sidewalks should be finished early in the week of Oct 12. 

Overview

DPU will manage replacement of approximately 4,600 linear feet of 8" cast iron pipe with new 12" PVC pipeline along San Ildefonso Road. The existing 8" pipe is aged and deteriorated and regularly requires repairs. The new 12" pipeline will increase the water supply to the North Mesa, improve reliability and fire protection, and add additional capacity to serve two proposed large housing developments.

Project area

aerial map of approximate workzone along San Ildefonso Road

Budget

  • Water Trust Board: $2,000,000
  • CIP: $300,000
  • Total: $2,300,000

 