Trinity Drive Electrical Replacement Project

  • Project typeElectrical utility upgrade
  • Project scheduleSummer - Winter 2026
  • Contractor nameDub-L-EE
map of Trinity from Oppenheimer to Timber Ridge with work zone marked in red box

Update

Phase 1 has been completed. Phase 2 is active on the south side of Trinity Drive, weather permitting. An initial press release was sent out June 12, regarding this project: Sidewalk work to begin on Trinity

Construction operations

  • North side of Trinity Drive is complete, as of August 21.
  • Crews will be working in the south side intersection of Trinity Drive and Oppenheimer Road through early October: removing sidewalk and installing fiber and electric conduit. 

Traffic control

  • To ease flow of traffic, please do not turn left onto Timber Ridge Road during high traffic times (there is currently no dedicated turn lane). Drivers are encouraged to only make the right turns onto Timber Ridge Road.  
  • Cones will be present in roadway and lanes will be shifted to allow safe workspace.
  • Follow all work zone signs and exercise caution.

 

Location

Trinity Drive from Oppenheimer to Timber Ridge, Los Alamos, NM 87544  View Map

Google Map